Works at Karrinyup have continued to progress well over the last month, with significant work underway to prepare for H&M’s new tenancy.

Further high-level details of works being carried on site this month are as follows:

  • New sections of ceiling being installed outside of new H&M
  • External façade works outside the new H&M box are nearing completion
  • New skylights are being installed for a small section of new mall outside H&M
  • Concrete for sections of the ground level fashion loop slab are being poured towards the north-east of site
  • Level 1 slab for northern section of fashion loop is also underway
  • Preparations are underway for construction for the roof to the new multi-deck car park

See the pace of construction in our time lapse footage from July, below.